Sharechat Logo

CHI - Q3 Conversion Project Update

Thursday 13th October 2022

Text too small?

Channel Infrastructure (CHI), New Zealand’s largest fuel import terminal business based at Marsden Point in Northland, has today released its quarterly conversion project update for the three months ended 30 September 2022 (Q3 FY22).

Key conversion project highlights for Q3 FY22 include:

• Six months of terminal operations successfully completed with 35 import shipments received and discharged;

• Permanent decommissioning of refinery plant is now over 70% complete and on track for completion of decommissioning in H1 FY23

• Significant workforce transition largely complete with 97% of those who have left having secured their next opportunity; and

• Conversion costs tracking to budget, with approximately $98 million spent project to date.

CEO Naomi James said “After six months of terminal operations, our business is now firmly focused on the future, with imported fuel flowing through our infrastructure and the first delivery of sustainable aviation fuel receipted into Marsden Point. We are progressing work to source lower cost renewable electricity, and have had significant interest in our RFI, while at the same time we continue to work with customers to support them with the import of fuels which offer more choice to consumers. We are delivering on our plans to utilise Marsden Point’s highly strategic assets to deliver long-term shareholder value, while at the same time supporting our customers to decrease their environmental impact in the future.”

Overall, the terminal and pipeline supplied nearly one-and-a-half billion litres of product to the Auckland and Northland markets since 1 April. Jet fuel throughput continues to grow steadily and is approaching 60% of pre-COVID levels. Further strong growth in jet demand is expected as more overseas airlines return to Auckland over the summer period and long-haul routes and capacity is added.

Decommissioning of refining plant continues to progress well and remains on schedule for completion in H1 2023.

Terminal upgrade works (including changes to increase vessel discharge rates and commissioning of the first fire-system and secondary-containment upgrades) and continued private storage tank conversion work is ongoing and progressing well.

The extensive workforce transition program is now largely complete. Channel Infrastructure had a target for at least 90% of employees securing a job or retraining within 6 months of leaving, and this has been reached with 97% of those who have left having secured their next opportunity.

Conversion costs are tracking to plan with $98 million spent to 30 September 2022 (30 June 2022: $73 million), including c$7m of private storage costs. The conversion spend, partly offset with positive cash flows from terminal operations, resulted in an increase in net borrowings from $215 million as at 30 June 2022 to $230 million as at 30 September 2022.

- ENDS -

CHI - Q3 Conversion Project Update



  General Finance Advertising    

Comments from our readers

No comments yet

Add your comment:
Your name:
Your email:
Not displayed to the public
Comment:
Comments to Sharechat go through an approval process. Comments which are defamatory, abusive or in some way deemed inappropriate will not be approved. It is allowable to use some form of non-de-plume for your name, however we recommend real email addresses are used. Comments from free email addresses such as Gmail, Yahoo, Hotmail, etc may not be approved.

Related News:

WCO - James Redmayne to resign from executive role
Fletcher Building Market Update
Devon Funds Morning Note - 13 May 2024
GTK - Half-Year Results Investor Briefing Details
GNE - Huntly Firming Options
Chatham Closes Private Placement
May 13th Morning Report
Rakon FY2024 Results Announcement Date
WHS - The Warehouse Group FY24 Third Quarter Sales Update
May 10th Morning Report